February 24, 2012

This weeks work? Feb. 24 to March 2

Week of Feb. 24 to March 2

Monday

Tuesday
Everyone
Turn in 3-4 elevations in the blog for discussion

Nick, Daniel, Perla
Go to Boston Resource Center @ 9am
Everyone
Have a skype meeting @ 11:30pm select two best for model making

Nick, Daniel, Perla
Start on the first full size model
Wednesday

Thursday
Peter, Nicole
Visit site to get the utilities location

Daniel, Peter
Start on Second full Size Model
Friday

Saturday/Sunday
Everyone
Be in class by Noon






Individual work:

·         Wall Sections

·         Research Hardware

·         Look into corrugated metal roofing colors

·         Look into corner designs for the new shed

·         Look into window catalogs, pick windows for shed

February 5, 2012

December 2, 2011 Meeting with Penny

Bellow please find the main issues discuss about the boards:

- Water will be better outside the shed
- The electric meters are in the right side of the current shed
- Maintenance free siding is preferable
- Windows makes lattice shed less stable, fix design of lattice shed
- Penny will like to see samples of permeable concrete and know more about how it works
-Currently the shed is greatly inefficient and tools are not organized inside
- The slope of the ramp is OK but the ramp is a little too long, it needs to be a little shorter
-  Color and material of roof still undefined
- Handicap Planters need to be incorporated in drawings
- Relocation of Shed leaves a space on top of hill, for potential Bulletin board or sign
- Need deeper studies of current spending, plan a budget and propose

you can find the boards in the following folder:

CharlestownCommunityGardenShed/FinalBoard 12-3-11/CCGS Final Design Boards 12-3-11 

-Perla Muller