October 10, 2011
Things to do for Wednesday; October,12!!!!!
October 9, 2011
Schedule for this Week (10/10/11 - 10/14/11)
Meeting for this Week
| Sunday (10/9/11) | | Monday (10/10/11) | ||
| No Meeting | Post work on the Dropbox. (Site Diagrams) | | Nick, Perla, Elle and Nicole | Meeting Time |
| | | | | 11pm |
| Tuesday (10/11/11) | | Wednesday (10/12/11) | ||
| No meeting | | | Elle, Nick and Nicole | Meeting Time |
| | | | | 1pm |
| Thursday (10/13/11) | | Friday (10/14/11) | ||
| No meeting | | | Everyone | Meeting Time |
| | | | | Before class in case we need more time to work. |
October 8, 2011
Things to be done for October 10, Monday:
Hi Team,
Here are the things we have to be done for Monday (10/10/11):
- Site Section (tow sections); NICK & PERLA
- Site drawing in CAD with measurements and surroundings; NICOLE
- Logo Design (bring just ideas); EVERY ONE
- Materials (photo); ELLE
Don't forget that each of us has to do the site diagrams for Monday. Don’t forget Monday 10/10/11 we are going to meet on Skype at 11pm. Please feel free to contact me or call me if you have any questions.
Best Regards,
Nicole Pinot-Juan
October 2, 2011
Things to do for October 3!!!!
Gateway Project – CHARLESTOWN COMMUNITY GARDENS – Fall 2011
___________________________________________________________________________________
Program
Location: Bunker Hill Community Facilities Subdistrict,
456-458 Bunker Hill street, Charlestown, MA 02129
Client: Gardens for Charlestown, inc.
Contact persons: Penny Carlhian, (Treasurer) Roberta MacCarthy, Robert Spencer
Team members: Elle Coleman, Nicholas Joelli, Nicole Pinot-Juan, Perla Muller
Project supervisors: Todd Lee, Rick Lamb, Pat Welsh
Budget: $12,000 - $15,000
Budget sources:
$40/year for plot fee, extra for greenhouse use
No established retail/commercial partners
$500 from Spalding to improve accessibility
Applied for $3,000 grant from Big Dig mitigation funds to improve accessibility
Access requirements/ Security:
ADA accessible to tool shed, accessible plots, and seating area
City leaf mulch deliveries
No regular waste pickup
Shed needs to be locked, but accessible to everyone with plot
-Code lock
Larger door for snow blower
Approximate value of supplies in structure: ~$2,500
Exterior lighting: motion sensor on new shed
Utilities:
Water/Electricity to existing shed
-Water lines ~15 years old
Durability:
Wood structure expected as replacement of existing structure
Typical items in structure: snow blower, lawnmowers, gas, assorted gardening equipment
Zoning: OS-CG (Community Garden Open Space Subdistrict)
setbacks: none
floor area ratio: 2.0
maximum allowed building height: 45'
Design:
Historical connections of site/community: no attachment to current design
Specific requests:
-Keep access to site welcoming to all
-Site is “gateway to community”
-Keep separation of patio space and garden/shed
-Maintain adequate sunlight on plots
Gateway Project – CHARLESTOWN COMMUNITY GARDENS – Fall 2011
___________________________________________________________________________________
MINUTES – Meeting with Client – 9/30/2011, 2:00 pm – on site Page 1
1. INTRODUCTIONS
Client Representatives – Penny Carlhian, Roberta MacCarthy, Robert Spencer
Team members in attendance – Elle Coleman, Nicholas Joelli, Nnicole Pinot-Juan (Perla Muller out)
Project Supervisors – Todd Lee, Rick Lamb, Pat Welsh
2. OLD BUSINESS
Changes to minutes from meeting on 9/9/2011 will add once posted
3. MEMORANDUM OF UNDERSTANDING
approved
4. PROGRAM
Budget estimated around twelve thousand ($12,000) to fifteen thousand ($15,000) dollars
Five hundred ($500) dollars from Spalding to improve accessibility
Applied for three thousand ($3,000) dollar grant from big dig mitigation funds to improve accessibility
Value of items in tool shed estimated around two thousand five hundred ($2,500) dollars
Consideration of unknown underground utilities removed
Durability of structure expected comparable to existing shed
5. SCHEDULE
Budget set around end of November
Final documents presented mid-December
Parts of design prohibitive in current program should be considered for phasing in the future, but shed should be operational as soon as possible.
6. DESIGN OPTION #2, #1 PRESENTED
Elements of design client representatives found appealing:
-Sliding barn style doors
-Rain water recovery
-Ivy covered sign
-Green roof (most likely in future phases)
-Utilization of space between tool shed and seating area.
Elements of design that require consideration:
-Option #1 requires large new foundation, and movement of utility meters
-Durable translucent materials instead of glass
-Shed used heavily by many people
-Designs could be more industrial and eccentric
Minutes/Program
-Nick