October 28, 2011
this weeks to do list
Door lock details - Nicole
Sketchup models - Nick
Accessible area design - Perla
Monday night skype meeting
October 25, 2011
to do
nicole: 3 lattice shed redesignes, roof design
elle: 3 wall sections, current inventory
nick: plan, diagram
meeting thurs 11:00 pm (skype)
Pozzolan Cement...
To be posted latest by tonight for some fedback!
October 23, 2011
Storage Shed Relocation Diagram
Bellow I attached some images of what I found online from searching Katsura Palace http://picasaweb.google.com/christopher.s.wils/JAPANJune2009GardensAndNature#
Todd please notify if this is what you were refering to.
October 20, 2011
October 18, 2011
budget
there are also some pictures of the products that wont show up on the blog, what do you think?
material | Unit price | Price source | Quantity | Total cost |
Lumber 2x4x10 2x6x10 23/32x4x8 |
$3 $6 $20 | The Home Depot |
25 7 20 |
$517 |
aluminum roofing | $4/foot | triad corrugated metal | 100 |
$400 |
Rainwater barrel (basic) (premium)→ | $150 $428 | Compost.com | 1
|
$159- $428 |
Previous concrete
| $2 - $7 / square foot | epa.gov | 1200 | $2400- $8400 |
Used pellets
| free | J B M Services Inc | 10 | $0.00 |
October 17, 2011
New Diagram
October 15, 2011
Responses to comments
How will you handle the electrical and water supplies and meters?
Is the existing lattice shed (plant shed) being moved or is your plan to build a new one? (I suggest that we propose a new structure, but you will need a design!)
Do you enter the garden through the shed?
Is that a new fence between the handicapped accessible area & garden?
What is the material for the handicapped accessible area? Concrete? Brick pavers? Concrete pavers? Stone dust?
How they get the snow blower out? Do they use the single swing door at the HP access area?
How would this work if the existing ramp was to remain but the shed was moved to the proposed location?
Where did the sliding barn doors go? If you keep the swing doors you might want to consider moving off center to avoid conflict w/ the planting bed.
What happens too or how do you resolve the trellis along the backwall of the upper area? Does it turn and create a gateway / opening from the top of the ramp to the brick patio?
How long is the ramp? 1:12 slope, so if the elevation change is 30" it = a 30' ramp. Longest run without at level landing is 30'. You need to be able to definitely answer the elevation change and how it affects the length of the new ramp. If you go with a slope of 1:20 then you need a ramp 50' long with a 4' level landing, but you can remove the railings.
Schedule for this Week (10/15/11 - 10/21/11)
Meeting for this Week
Saturday/ Sunday (10/15/11 – 10/16/11) |
| Monday (10/17/11) | ||
No Meeting |
|
| Nick, Perla, Elle and Nicole | Meeting Time |
|
|
|
| 11pm |
|
|
| Post all due Work on Dropbox |
|
|
|
|
|
|
Tuesday (10/18/11) |
| Wednesday (10/19/11) | ||
No Meeting |
|
|
| Meeting Time |
|
|
|
| If it’s need it. |
|
|
| Expecting to conclude the work. |
|
|
|
|
|
|
Thursday (10/20/11) |
| Friday (10/21/11) | ||
No Meeting | Working with the Finals Boards. |
| Everyone | Meeting Time |
|
|
|
| 1pm at BAC |
|
|
|
|
|
List of what we have to be working on!!!!!! due: Wednesday (10/19/11)
Here is the list of what we have to be working on, for the Presentation on Friday (10/21/11):
-Diagram (scale: 1/8” = 1’-0”); PERLA
-Final Presentation Boards; PERLA
-Plan View & Elevations (scale: ½” = 1’-0”); NICOLE
-Section Details; NICOLE
-Materials Precedents; NICK
-Budget Graph.; NICK
-Tow Sections (scale: ½” = 1’-0”); ELLE
best regards, Nicole Pinot-Juan
Things to be done for October 17, Monday:
Hi Team,
Here are the things we have to be done for Monday (10/17/11):
- Materials Precedents (graph.); NICK
- Budget; NICK
- First Board Layout; PERLA
- Material Board from Site; ELLE
-Post the idea of layout that you are going to use for the materials board no later than Saturday; ELLE
Don't forget we have the meeting Monday (10/17/11) at 11pm.
October 14, 2011
Diagram for review!
October 13, 2011
Reminder!!! :)
October 12, 2011
Yes we need to raise the Shed and yes the budget is five digits!
You have have stated the floor level well. In raising the floor elevation, we need to make a clear and convincing proposal for doing so that relates to elevations beyond the shed itself. See you all Friday.
If any of you have time, see if there are images of the Provincetown Art Association Museum. Some of the wall details are very interesting.
Rick
On Oct 11, 2011, at 6:02 AM, Lee Todd wrote:
> PERLA -
>
> 1. Raising the storage shed
> All schemes that we have agreed upon need to raise the floor level of the shed to respond to raising the ground level outside, since it is necessary to cure the low spot and water collection. So do incorporate this move in your solutions and the budget.
>
> 2. Budget Limit
> Generally the client has put the budget at $12,000 to $15,000 which is stated correctly in the Minutes. However, we have have discussed that if there are design proposals which merit increasing that amount, they would be dealt with by:
> (a) raising more money through additional grants, or fundraising for the current project, or
> (b) phasing - doing additional work as a later phase(s). Note that with this strategy the first phase must not be left with some sections not useful. The Gardens must be functional at the end of each phase - for example, in the option to relocate the lattice pavilion, that structure would not be demolished and the ground restored to another use, until the new pavilion was complete, and the pavilion functions relocated.
>
> PAT, RICK -
> please add, comment or correct.
>
> TEAM -
> I regret that I will not be in town to see the progress you have made. There were some strong design ideas in the works last week. The client has agreed to participating in our Final design presentation week after next , 10/21.
>
> TODD
>
>
> TODD LEE FAIA LEED AP - ARCHITECT
> 85 EAST INDIA ROW - 32H BOSTON MA 02110
> 617 320 3782 VOICE TXT
>
> todd@toddleearchitect.com
>
>
>
> On Oct 11, 2011, at 1:39 AM, Perla Muller wrote:
>
>> Hi Todd,
>>
>> We had a question in regards to raising the storage shed. Are we to consider this option and incorporate into our design? or this is out of the conversation and budget?
>>
>> Also there was some confusion about the budget we would like you to clarify, can you tell us what is the budget as of now. We are doing some material research and would like to take this into consideration when we pick materials for our design.
>>
>> thank you,
>>
>> Perla
>>
>
Things to be done by Friday, (10/14/11)
Hi Team,
Here are the things we have to be done for Friday (10/14/11):
- Research: Basin (water collector and how it connect with the roof) and
Corrugate Metal Roof; NICK
- Budget List and Detail Drawing connection of Roof; NICK
- Elevations and Plan View; NICOLE
- Research: Insulation Materials for Sheds and Interior Material; PERLA
- Sections Drawings through site (slope of site); PERLA
- Board of Existing Material on Site; ELLE
- Interior Elevations and Sections; ELLE
Remember to bring the research material that we are working on. Thank you guys to be able to put together our ideas for the Shed. Exited to see you Friday, 10/14/11. Good job team!!!
Best Regards,
Nicole Pinot-Juan
October 10, 2011
Things to do for Wednesday; October,12!!!!!
October 9, 2011
Schedule for this Week (10/10/11 - 10/14/11)
Meeting for this Week
Sunday (10/9/11) | | Monday (10/10/11) | ||
No Meeting | Post work on the Dropbox. (Site Diagrams) | | Nick, Perla, Elle and Nicole | Meeting Time |
| | | | 11pm |
Tuesday (10/11/11) | | Wednesday (10/12/11) | ||
No meeting | | | Elle, Nick and Nicole | Meeting Time |
| | | | 1pm |
Thursday (10/13/11) | | Friday (10/14/11) | ||
No meeting | | | Everyone | Meeting Time |
| | | | Before class in case we need more time to work. |
October 8, 2011
Things to be done for October 10, Monday:
Hi Team,
Here are the things we have to be done for Monday (10/10/11):
- Site Section (tow sections); NICK & PERLA
- Site drawing in CAD with measurements and surroundings; NICOLE
- Logo Design (bring just ideas); EVERY ONE
- Materials (photo); ELLE
Don't forget that each of us has to do the site diagrams for Monday. Don’t forget Monday 10/10/11 we are going to meet on Skype at 11pm. Please feel free to contact me or call me if you have any questions.
Best Regards,
Nicole Pinot-Juan
October 2, 2011
Things to do for October 3!!!!
Gateway Project – CHARLESTOWN COMMUNITY GARDENS – Fall 2011
___________________________________________________________________________________
Program
Location: Bunker Hill Community Facilities Subdistrict,
456-458 Bunker Hill street, Charlestown, MA 02129
Client: Gardens for Charlestown, inc.
Contact persons: Penny Carlhian, (Treasurer) Roberta MacCarthy, Robert Spencer
Team members: Elle Coleman, Nicholas Joelli, Nicole Pinot-Juan, Perla Muller
Project supervisors: Todd Lee, Rick Lamb, Pat Welsh
Budget: $12,000 - $15,000
Budget sources:
$40/year for plot fee, extra for greenhouse use
No established retail/commercial partners
$500 from Spalding to improve accessibility
Applied for $3,000 grant from Big Dig mitigation funds to improve accessibility
Access requirements/ Security:
ADA accessible to tool shed, accessible plots, and seating area
City leaf mulch deliveries
No regular waste pickup
Shed needs to be locked, but accessible to everyone with plot
-Code lock
Larger door for snow blower
Approximate value of supplies in structure: ~$2,500
Exterior lighting: motion sensor on new shed
Utilities:
Water/Electricity to existing shed
-Water lines ~15 years old
Durability:
Wood structure expected as replacement of existing structure
Typical items in structure: snow blower, lawnmowers, gas, assorted gardening equipment
Zoning: OS-CG (Community Garden Open Space Subdistrict)
setbacks: none
floor area ratio: 2.0
maximum allowed building height: 45'
Design:
Historical connections of site/community: no attachment to current design
Specific requests:
-Keep access to site welcoming to all
-Site is “gateway to community”
-Keep separation of patio space and garden/shed
-Maintain adequate sunlight on plots